China I Changzhou plant, Jiangsu province Key facts of the plant: 1 • 1st EAFD recycling plant in China • . Capacity to recycle 110kt EAFD p.a. Total investment: c.€42m Location: Changzhou (Jiangsu province) Status update: ✓ Long-term financing closed Jul'20 Construction completed on budget In commercial production & selling WOX Contracted EAFD for >80% plant utilisation in 2022 ↑ Changzhou plant, in operations ↑ First commercial invoice China II Xuchang plant, Henan province • Key facts of the plant: • 2nd EAFD recycling plant in China • Capacity to recycle 110kt EAFD p.a. Total investment: c.€42m Location: Xuchang (Henan province) Status update: ✓ Long-term financing closed Dec'20 Construction completed Dec'21 on budget 2 2 → Commissioning started; Expecting ramp up H1'22 & commercial output H2'22 10 0/ Company Presentation - April 2022 11111 111111111 ↑ Xuchang plant, construction completed - 27 December 2021 BEFESA