ANNUAL REPORT 2021-22
20
Outages and works
21
ANNUAL REPORT 2021-22
ANNUAL REPORT 2021-22
Territory Generation's outage planning program is critical to our business. We forecast and conduct
outages and works to maintain our generating units and ensure the delivery of safe, reliable and
cost-effective electricity services. Our outage planning scope includes machine replacements,
upgrades, maintenance, repairs, and improvements.
Darwin-Katherine
interconnected system
CHANNEL ISLAND
AND WEDDELL GAS
SUPPLY
Gas for Channel Island and
Weddell power stations is
supplied by Power and Water
Corporation from Eni's Blacktip
field. In the event Blacktip is
unavailable, emergency gas
has been supplied by Darwin
LNG. However, as production at
Darwin LNG is forecast to slow,
INPEX has been contracted by
PWC as an additional emergency
supplier. INPEX gas from the
Ichthys field is export quality,
which means it has been
stripped of inert gases and has
approximately 17 per cent more
energy content. We carried out
crucial trials at Channel Island
and Weddell power stations
to test if our machinery could
handle the transition to higher-
energy gas and back again. Both
trials were deemed successful.
CHANNEL ISLAND
C8 is a Siemens aero-derivative
turbine which was scheduled
for a mid-life overhaul and hot
section exchange at 35,000
hours. In 2020, we removed the
turbine for transport and repair
by Siemens in Abu Dhabi and
replaced it with a lease unit.
132 KV CABLE
REPLACEMENTS
PROGRAM
Replacement of the ageing
132 KV cables from the
generator set-up at Channel
Island Power Station are now
90% complete with only C1
installation remaining. The works
were postponed until 2022 to
align with Power and Water
Corporation switch yard works.
WEDDELL
The W2 annual outage in
May found the engine to be
unserviceable. It was replaced
with the on-hand spare Weddell
engine. A new engine will replace
the W3 engine at Weddell
Power Station later in 2022
when its service hours have
been consumed. Procurement
of a new Weddell engine has
been completed and delivery is
anticipated before 30 June.
Southern region
OWEN SPRINGS
OSO3 is one of three MAN 10.9 mW medium-speed reciprocating
dual-fuel engines that provide inertia and improve the security
of the Alice Springs power system. Its 16,000-hour service was
completed in July 2021. Work included the removal of all cylinder
heads and replacement of pilot injector tubes, required because
the other two MANS had already been upgraded. Heads were
pressure tested and refitted back onto the engine. All pilot
injectors and gas valves were then installed. All the work was done.
by our own team.
KINGS CANYON
KCO2 is one of three engines at the Kings Canyon Power Station.
KC01 and KCO2 are 400 kW QSX15 Cummins diesel engines and
KC03 is a 200 kW QSL9 Cummins diesel engine. KC02 was replaced
with the original KC03 after its scheduled overhaul, which was
completed in December 2021 by contractors and internal personnel.
TENNANT CREEK
TC19 is one of three Jenbachers installed at Tennant Creek Power
Station in 2017. TC19, TC20 and TC21 are spark-fired engines rated
at 1.8 MW. The TC19 head was replaced in September 2021 at the
due 10,000 hours by internal personnel and contractors.
Graduate Mechanical Engineer, Steven Sawyer, inspects Weddell W2.
ial Controls
Electrical and maintenance works
at Ron Goodin Power Station.View entire presentation