Minas-Rio Impairment Considerations and Project Delivery
KEY SHORT TERM SCHEDULE RISKS
Mine
Context
FOOS date impact
In the event of a 3-6 month
delay (from cut-off date)
Comments
•
•
Cave 1 suppression
and Mine Access
Beneficiation Plant
TL 230kV land
release (Beneficiation
Plant)
Cave impacts the pre-stripping
activities
• New mine access being licensed
• Legal injunction lifted
•
Release of land and access
H1 2015
(rainy season)
Active engagement with
authorities
•Authorisation anticipated in H1
2013
Extension of LI
H1 2015
(rainy season)
23% of towers released for
construction since December
2012
O Contractor mobilised
•
Closure of Tailings
Dam
• Land access available (November 2012)
Archaeological site recovery in progress
H2 2015
(dry season needed)
• Archaeological recovery
underway
Sites identified and prioritised
Pipeline
•
Front 1 access
Nova Era Silicon's (NES) Legal
Reserves relocation
National road - LMG 790 accesses
H1 2015
(rainy season)
.
53% of NES earthworks
released
25% of LMG 790 earthworks
released
10View entire presentation