Quellaveco on track for mid 2022 delivery PARE Anglo American Operations-Autonomous haul trucks CARA CARGADO DE VIDA Y SEGUR 01 Quellaveco Greenfield copper project On track for mid 2022 delivery despite Covid challenges First ore delivered October 2021 ● Processing plant - Line 1 ~90% complete, pre-commissioning underway Water dam complete - provider of year round freshwater to communities 100% renewable electricity On budget: $0.7-0.8bn22 capex to go (our share) FY 2021 capex ~$0.8bn22 (our share) Upcoming 2022 milestones on track Completion of 95km freshwater pipeline Primary crusher commissioning Completion of processing plant ● ● ● . 28